This page provides information about current or upcoming capital works projects in the City of Subiaco.

The following resurfacing works will commence from 28 August 2017 (works were delayed due to inclement weather) and the anticipated duration of works for all six roads is eighteen days. Should you have any queries, contact Luke McGuirk, Project Engineer, on 9387 0934.

Resurfacing works

Location

Status

Luth Avenue
Clubb Avenue to Cunningham Terrace

Resurfacing completed, linemarking to be reinstated

Troy Terrace
Stubbs Terrace to Jersey Street

Resurfacing completed, linemarking to be reinstated

Troy Terrace
Hay Street to Robinson Terrace

Resurfacing completed, linemarking to be reinstated

Roberta Street
Wilsmore Street to Jersey Street

Wednesday 6 September 2017

Cunningham Terrace
Roberta Street to Millington Street

Wednesday 6 September 2017

Streetscape improvement works

Location

Status

Roydhouse Street
The next stage of the streetscape improvement project from Centro Avenue to the cul de sac

Monday 4 September 2017 (2 weeks)