Rokeby Road planter box maintenance
Friday 3 February 2017
 

Please be advised that scheduled works, which require localised road closures along Rokeby Road, will take place until Wednesday 22 February. Working at night in order to minimise disruption, the city’s contractors will be making adjustments to the Rokeby Road irrigation system and also levelling the ground underneath the planter boxes.

Works will take place along the median strip, with no earthworks or excavations involved. Traffc management will be in place, and access to footpaths and alfresco areas will continue as normal.

Planned work schedule:

Section

Expected dates

Affected lane

Roberts Road to Seddon Street

9, 12 February

Northbound

Seddon Street to Hay Street

7-8 February

Northbound

Hay Street to Churchill Avenue

5-6 February

Southbound

Churchill Avenue to Barker Road

13, 15, 16 February

Northbound

Barker Road to Bagot Road

19-21 February

Southbound


For project enquiries, please contact Kirk Linares on 9387 0912.